Shell-Only Loft Conversions in Halesowen
Planning a shell-only loft conversion in Halesowen? We survey the roof, produce the drawings, deal with approvals and build it, with a guide price of £24,000 to £44,500 including VAT for the West Midlands.
- Free home survey
- Fixed written quote
- Drawings and engineer included
- Building control handled
- UK-wide teams

Shell-Only Loft Conversions for homes in Halesowen
Halesowen is a large town in the West Midlands, about 4 miles from Dudley. Our surveyors cover the whole area, so a visit can usually be arranged within a few days.
Inter-war semis with hipped roofs are everywhere, which makes hip to gable with a rear dormer the standard job.
What does a shell-only loft conversion cost in Halesowen?
Prices in Halesowen follow our guide rate for the West Midlands, which is in line with the national guide. That puts a shell-only loft conversion at £24,000 to £44,500 including VAT. Your fixed quote follows the survey and sets out each stage payment.
| Guide price in Halesowen | £24,000 to £44,500 inc. VAT |
|---|---|
| Typical duration | 3 to 6 weeks on site |
| Survey and quote | Free |
Key facts
- First-fix cables and pipes are usually best included in the shell so they are in before insulation and boarding.
- Lenders and insurers may want to see the completion certificate, so plan to finish within a reasonable period.
- We provide the engineer's details and drawings your finishing trades need.
- Fire doors, smoke alarms and the protected stair are part of final sign-off, so they must be in your finishing scope.
Why use us in Halesowen?
- Matching tiles, slate and brick sourced for a roofline that fits the street.
- Structural engineer's calculations on every project.
- Scaffold access through the roof, so the house stays usable.
- Snagging visit after completion.
Planning and building control in Halesowen
Planning and building regulations apply in the same way; the completion certificate is issued when the finished work is inspected.
Building regulations approval is always needed. Building control checks the structure, fire safety, stairs, insulation, ventilation and electrics and issues a completion certificate at the end.
Where beams bear on a shared wall, the Party Wall etc. Act 1996 requires written notice to the adjoining owner at least two months before work starts.
How the work runs
Free home survey
A surveyor measures the loft, checks head height and roof structure and talks through what you want from the room.
Design and fixed quote
You receive layout options and a written, itemised price that does not change unless you change the design.
Approvals
We submit planning or lawful development applications where needed and deal with building control.
Finish and certificate
Plastering, second fix, decorating and the final inspection, after which you receive the completion certificate.
Shell-Only Loft Conversions in Halesowen: your questions
Is the survey in Halesowen really free?
Yes. The survey and quote are free. Drawings and calculations are charged only once you decide to go ahead.
Do I need planning permission in Halesowen?
Planning and building regulations apply in the same way; the completion certificate is issued when the finished work is inspected. We confirm the position with the local planning authority before work starts.
Will a loft conversion suit my house in Halesowen?
Most houses can be converted. The checks are head height under the ridge, roof pitch, the type of roof structure and where the stairs can go. We measure all four at the survey.
How long does it take?
Allow 3 to 6 weeks on site to shell stage.
What is included at shell stage?
The structure, weatherproof envelope, windows and stairs as standard. Insulation and first-fix services are optional extras we recommend.