How long does a loft conversion take?

Building work for a loft conversion takes about 4 to 6 weeks for a rooflight conversion, 6 to 10 weeks for a dormer, 8 to 12 weeks for a hip to gable and 10 to 14 weeks for a mansard. Add 6 to 10 weeks beforehand for survey, drawings, structural calculations and party wall notices, and about 8 more weeks if planning permission is needed.

Before work starts

Survey and design take two to three weeks. Structural calculations and building regulations drawings take a further two to four. Party wall notices need two months unless the neighbour consents sooner. Planning applications are normally decided in eight weeks.

Weeks one to three

Scaffolding is erected, materials are loaded through the roof, steel beams and floor joists are installed and the dormer or gable is framed. The aim is to have the roof weathertight as early as possible.

The middle weeks

Roof coverings, windows and insulation are completed. The staircase is fitted and the opening made into the landing below. First-fix electrics and plumbing follow and are inspected.

The final weeks

Plasterboard and plaster, second-fix joinery, bathroom fitting, electrics and decorating. Building control makes its final inspection and the scaffold comes down.

What causes delays?

Late design changes, slow party wall responses, bad weather while the roof is open, and long lead times on bespoke stairs or windows. Fixing the design before the start date avoids most of them.

Last reviewed November 2026. This guide is general information; rules vary by nation and council, and we confirm the position for your address at survey.